Pictures !
of
< Return > ---
to the Spring
Division’s main site page
![]()
Overview - a Walking Tour to
the railroad, photo slideshow visit and
summary
1/6/10
- Hard shell and Rock work in the Midway area
5 / 09 - Durango Station is
finished and ready to install
4/17/09 -
4/2/09 - Durango Turntable
is detailed, installed and working
4/1/09 - Durango Sand
House is built and ready to place
1/5/09 -
10/22/08 - The Durango
Turntable is now installed and turning engines
4/26/08a - ProRail
2008, Crews operate on the railroad on Saturday, pictures by Frolin
4/26/08b - ProRail
2008, Crews operate on the railroad on Saturday, pictures by
4/24/08a - ProRail
2008, Crews operate on the railroad on Thursday, pictures by Frolin
4/24/08b - ProRail
2008, Crews operate on the railroad on Thursday, pictures by
Jan/Feb/Mar check back later to
see photos of work early in 2008 being added shortly
11/9/07
- Brown paper is up
and some more photos of the hard shell starting
9/29/07 - More brown Paper
starts going up to prepare for an open house
11/27/06 - Brown paper is up
and some more photos of the hard shell starting
11/12/06 - More brown Paper
starts going up to prepare for an open house
10/20/06
- Another trestle
goes in, scenery gets added and progress continued
4/18/06 - April has a new trestle going in on the branch line, near
Stony Creek
10/18/05
- Rock Molds
covers the Stony Creek area, just in time for San Jac
2005
10/4/05
- End of September and early October, color and ground cover
on the rock casting
9/9/05
- Early September and rock casting work has starting
8/18/05
- Mid August 2005 and the rock molds are going up! (early pictures
only)
8/17/05
- Early August 2005 and brown paper starts to get hard shell
5/2005
- May 2005 hard shell starts in
11/2004
- November 2004 the hard shell started going up for scenery
8/2004
- August 2004 and the tracks have reached Spring
7/2004
- July 2004
has trains passing Rio Chama and closing in on Spring
6/2004 - June 2004, progress before the LSR Open House, trains reach Rio Chama
10/2003
- October 2003 shows the layout, with standard and narrow
gauge engines
8/2003
- August 2003
layout progress, with the lower storage yard installed
2002
- Benchwork
construction goes in and then track work is started
2001
- The
construction of the train room starts in 2001.